Quality System Certification
  _ Previously Motorola Korea Limited founded in March 1967
_ ISO9002 certified by SGS-Yarsely in December 1993.
_ QS9000 certified by LRQA(Lloyd Register Quality Assurance)
   in June 1997 with the remarkable comment of ¡°SECOND TO NONE¡± facility
_ Continuous Zero Non-Compliance from LRQA¡¯s Surveillance or Special
   Audits
_ TS16949 certified by LRQA in August 2003
  Assessment History

Environment Control
  Utility Control
   _ N2 in-house facility and LN2 & Hydrogen supplied by outside vendor
   _ Gas purity and moisture monitor
   _ DI water control for bacteria, resistivity and total organic carbon
Item Control limit

Bacteria

10 colony/cc

Resistivity

14 mega ohm

Organic Carbon

1 ppm

  Temperature/Relative Humidity Control
   _ Computerized BAS(Building automation system)
       Real time monitor and control temperature and relative humidity
       Sensor on every 5000 sq. ft and alarm when out of control limit
   _ Specification
Item Control limit

Temperaturea

22+/-5 C

Humidity

45+/-15%

  Particle Control
   _ Clean room is designed per FED-STD-209D & IES-RP-CC012
   _ Positive air pressure control, differential pressure(>0.2mmAq.) with real
      time BAS monitoring on the line requiring <1000 particles
   _ Particle monitor with portable counter once/month
Class Control limit

10(0.5 micron)

10/cubic feet

1K

1K

10K

10K

100K

100K

  ESD Control
Conductive Floor Surface Resistivity 105 - 109 Ohms/Square

Dissipative Smock

Surface Resistivity

105 - 1011 Ohms/Square

Dissipative Shoes

Surface Resistivity

105 - 1011 Ohms/Square

Ionizer Control

Decay Time(1000v ¡æ100v)

< 10 seconds

 

Balance (volt)

< 35 volt

Equipment

Resistance to Ground

< 10 Ohms

Work table

Table mat top to Ground

105 - 109 Ohms

Conductive Chair

Seat to Floor Resistivity

<109 Ohms

New Product/Process Introduction
 

Piece Parts Qualification
 

Supplier Quality Control
 

Process Control Cycles
 

Corrective Action Development
  _ Immediate Corrective Action as a Containment within 24 hours
_ System Review for Following Items
       What is the Current Quality System/Practice
       What are the Opportunities in addition to
       System Development covering all Opportunities
       System Institutionalization Across the Company
_ Documentation within 7 calendar days- 8D Methodology
_ Verification Audits / Effectiveness of Implementation
_ Management Review

Statistical Process Control
 

Data Collection and Sharing